Lansdowne Park Construction Update – Week September 30, 2013
On Sunday, September 29 a new crane will be put up on the west side of the Civic Centre, close...
On Sunday, September 29 a new crane will be put up on the west side of the Civic Centre, close...
The main entrance to the site will be moved back to the signalized intersection on Bank Street. At the southern...
During the week of July 29, a large continuous concrete pour will be conducted near the Bank Street Bridge. A...
The urban park at the redeveloped Lansdowne Park will be ready for public use when the CFL kicks off in...
The Lansdowne redevelopment contractor plans to pour a large foundation slab beginning on Tuesday, July 30 in the southwest corner...
Over the next couple of weeks residents will notice there will be some activity in the closed lane of Bank...
After a prequalification process, D&G Landscaping was ultimately chosen by the City of Ottawa’s to Build the Urban Park at Lansdowne....
The site will be closed on Monday, July 1 for Canada Day. Backfilling along the northern edge of the garage...
Activity will continue in the urban village and construction of the underground parking garage. The contractor for the building at...
Beginning on Thursday, June 20 the contractor will be backfilling along the Holmwood edge of the garage between Bank Street...