Lansdowne Park Construction Update – Week July 8, 2013

This week there will be a few days of piling between the west side of the stadium and Bank Street which could create some noticeable activity for residents near the Bank Street Bridge. Work has started to build the concrete walls and columns for the building at the corner of Bank and Holmwood and will continue for several months to complete the structure.
Towards the end of next week some additional piles will be placed on the north side of the Aberdeen Pavilion. This work will likely continue into the following week.
Backfilling activities along the edge of the parking garage which needed to be conducted from Holmwood are now complete. Thank you for your cooperation during this activity.