Lansdowne Park Construction Update – June 21, 2013
Activity will continue in the urban village and construction of the underground parking garage. The contractor for the building at...
Activity will continue in the urban village and construction of the underground parking garage. The contractor for the building at...
Beginning on Thursday, June 20 the contractor will be backfilling along the Holmwood edge of the garage between Bank Street...
This week the contractor anticipates the construction of the next new building will begin. This building is referred to as...
The contractor plans to pour a large foundation slab on Saturday, June 15 on the west side of the Civic...
Early next week, residents will see the start of building construction in the urban village area. Tall, structural beams for...
Work on the structural supports for the underground garage roof will move south closer to the Civic Centre and away...
Construction for the week of April 22 will continue in the Lansdowne urban village area to build foundations for the...
The compaction work near the west side of the Horticulture Building will be finished early next week and the machine...
Several activities will carry on next week at Lansdowne. Soil compaction work is anticipated to continue along Bank Street and...
The last stage of soil compaction work at Lansdowne will begin on Monday, March 11 and may last up to...