Lansdowne Park Construction Update, Week January 27, 2014
Next week the contractor plans to begin work on the roof of the Horticulture Building, located across from the corner...
Next week the contractor plans to begin work on the roof of the Horticulture Building, located across from the corner...
The contractor has reached the top of the office tower on Bank Street, and next week there will be activity...
Over the weekend, the main power for Lansdowne will be shut off in order to complete the new electrical connection...
Two activities next week will be visible along Holmwood. Early next week the contractor will be pouring concrete for the...
Activity will continue in the urban village and construction of the underground parking garage. The contractor for the building at...
This week the contractor anticipates the construction of the next new building will begin. This building is referred to as...
Construction activities will continue to be active in the urban village as work continues to build the garage on the...
Construction activities will continue next week at Lansdowne as additional columns and walls to support the underground parking garage are...
Early next week, residents will see the start of building construction in the urban village area. Tall, structural beams for...