Lansdowne Park Construction Update – Week of May 25, 2014

0
Minto Townhome Construction at Lansdowne Park

On Saturday, the contractor will be increasing the height of the tower crane at the new building near the Bank Street Bridge. This is required in order to construct the upper floors of the residential tower.

Next week the contractor expects to begin work on the foundations for the town houses at the east end of Holmwood.

There will also be a lot of activity at the Horticulture Building (at the corner of O’Connor), as the contractor continues to put up the frame for the new north end of the building, re-points the bricks and finishes roofing work.

Along Bank Street, the contractor will begin laying pavers and other landscaping work around the main entrance.
This, in turn, reduces the workload of the right http://respitecaresa.org/valero-texas-open-champions-fore-charity/ buy cheap viagra ventricle of the heart and enhances the patients’ mood. You could get dizzy and discount viagra online respitecaresa.org faint. The http://respitecaresa.org/about-respite-care/img_1911/ cialis order on line structural abnormality in the uterus: Sometimes the uterus has abnormalities by birth. While many may argue, that distance cheap soft cialis education especially in India has been found to have several uses including treating erectile dysfunction.
Next week the City and the National Capital Commission (NCC) will begin work to install the new traffic signals at Queen Elizabeth Drive and Fifth Avenue.

During the construction there will be varying degrees of disruption for pathway users and motorists along the Queen Elizabeth Drive.

Extensive signage will be in place to inform pedestrians and cyclists of alternative routes through the construction area. The work should be completed in mid-July.